Settlement Documents

Affected Period

Status
Closed

Category
Settlements

Run type
N/A

Created
24/07/2020 12:01

Last Updated
24/07/2020 16:27

Update 24.07.2020 @ 16:25

Dear Market Participant,

Please note that the payment due out date for the below MO Invoice will be extended in the Settlement Calendar by one business day (due to the 03rd August bank holiday).

Please use the payment due out date of the 04th August for MO. The payment due in date of the 31st July remains correct.

Apologies for any inconvenience caused by this issue.

Kind regards 

SEMO Settlements


Original:

Settlement Documents were successfully published this morning and are available for download for the following dates: 

The Settlement Document will contain:

• INITIAL BALIMB - (12/07/20 - 18/07/2020) - Week 28 2020

• M4 BALIMB - (29/03/20 - 04/04/20) - Week 13 2020

• M13 BALIMB - (03/03/19 - 09/03/19) - Week 09 2019

• M4 CRM March 2020

MO Invoice for:

• M4 CRM March 2020

 

Kind regards,

SEMO Settlements