Application of the Gross DRF for T-2 and onwards
Affected Period
Status
Closed
Category
Capacity
Run type
Created
21/06/2021 11:12
Last Updated
26/09/2023 10:07
Dear Market Participants,
Please be advised that the following Final Capacity Auction Results Reports have been republished on the website today:
- T-2 2021-2022 Final Capacity Auction Results Report
- T-4 2022-2023 Final Capacity Auction Results Report
- T-4 2023-2024 Final Capacity Auction Results Report
- T-4 2024-2025 Final Capacity Auction Results Report
As stated in the Version History tables of the T-2 2021-2022, T-4 2022-2023 and T-4 2023-2024 Reports, the Gross De-Rating Factor (FDERATE?) that applies to the Grid Code Commissioned Capacity when determining the Proportion of Delivered Capacity for the purposes of Substantial Completion, was added in Table 4 of each document. The objective of this update is to ensure there is clarity on the applicable Gross De-Rating Factor for the purposes of achieving Substantial Completion.
Please see below for reference:
Version
History
Version |
Update |
Date |
1.0 |
|
|
1.1 |
Included
the Gross De-Rating Factors for Awarded New Capacity in Table 4. |
21/06/2021 |
The T-4 2024-2025 Report contains only a formatting correction to the heading of Table 3. Please see below for reference:
Version
History
Version |
Update |
Date |
1.0 |
This report
is identical to the Provisional Capacity Auction Results Report published on
10/02/2021. The only addition is the inclusion of the Gross De-rating Factors
for Awarded New Capacity which is displayed in Table 4. Also, the Company
Name for GU_404010 has been corrected from Statkraft Ireland Ltd to Statkraft
Markets GmbH. |
12/03/2021 |
1.1 |
Corrected
the formatting issue for Table 3 heading |
21/06/2021 |
The updated reports can be accessed via the links provided above.
Kind
regards,
Capacity
Market Team
P: 1800 726772 (ROI) or 0800 0726772 (NI)
+353 (1) 2370584 (International)