Dear Capacity Market Participants,
The System Operators have published an updated version of
the Final Qualification Results Report for the 2022/2023 T-1 Capacity Auction
(FQR2223T-1). This document can be viewed on the SEMO website - here.
Version |
Update |
Date |
1.0 |
Approved Final Qualification
Results |
11/10/2021 |
1.1 |
Correction to Gross De-Rated Capacity (New) and Net De-rated Capacity
(New) for Demand Side Units to include 7.025 MW omitted in version 1.0 |
14/10/2021 |
1.2 |
Correction to Gross De-Rated
Capacity (Existing) and Net De-rated Capacity (Existing) for Demand Side
Units to include 1.98 MW omitted in version 1.0 and 1.1 Correction to Gross De-Rated
Capacity (New) and Net De-rated Capacity (New) for Demand Side Units to
remove 0.021 MW added in version 1.0 and version 1.1 Correction to Gross De-Rated
Capacity (New) and Net De-rated Capacity (New) for Other Storage Units to
remove 14.625 MW added in version 1.0 and version 1.1
|
20/10/2021 |
Capacity Market Team