Dispute Resolution Board (DRB) Findings
Affected Period
Status
Closed
Category
Balancing
Run type
N/A
Created
17/08/2023 10:15
Last Updated
17/08/2023 10:17
Dear
Market Participant,
We wish
to inform you of a recent decision of a DRB, in respect of a Balancing Market Dispute between a Market Participant and SEMO.
In its
decision, the DRB confirms (among other things) that the reference in paragraph
B.19.5.1(d) of the Trading and Settlement Code to ''equitable basis'' relates to procedural matters and does not afford parties with a substantive
remedy in equity.
The
relevant Market Participant has issued a notice of dissatisfaction in respect
of this DRB decision.
We are
issuing this market message in furtherance of the objectives of the Trading and
Settlement Code - in particular, to provide transparency in the operation of
the Single Electricity Market (paragraph A.2.1.4(e) of the Trading and
Settlement Code).
Kind
regards,
SEMO Team