Revised Weekly Constraints Update

Affected Period

Status
Closed

Category
Balancing

Run type

Created
07/10/2024 12:36

Last Updated
07/10/2024 13:28

Dear Market Participant, 

EirGrid and SONI have published a revised weekly constraints update for the current Week 41 2024.

The revision note:

The below temporary Transmission Constraint Group notes have been removed:

  • 'For ROI, MP1 and MP2 are must run when wind generation < 1000 MW.'
  • 'For ROI, Th1,TH2,TH3,&TH4 run hours are restricted in order to manage constraints in the greater Dublin area.'

The weekly constraints update is published every Friday evening on the General Publications page of SEM-O.com. 

Kind regards, 

SEMO Team