2027/2028 T-4 Capacity Auction Update
Affected Period
Status
Closed
Category
Capacity
Run Type
Created
Last Updated
Dear Market Participants,
In accordance with D.2.1.16 of the Capacity Market Code, the Regulatory Authorities have instructed the System Operators to publish an updated Capacity Auction Timetable for the 2027/2028 T-4 Capacity Auction. In accordance to paragraph D.2.1.11 of the Capacity Market Code (CMC), an updated version of the timetable is available here.
The amended timetable moves the Capacity Auction Run Start Date out by 4 weeks. The reason for this change is due to the TSOs managing a high number of key operational priorities within the Capacity Market workstream. The table below shows the impact of the delay on the impacted milestones.
Milestone |
Previous Timetable Date |
Amended Timetable Date |
Final Qualification Submission Date |
16/08/23 |
14/09/23 |
Final Locational Capacity Constraint Limits Date |
07/09/23 |
05/10/23 |
Final Qualification Results Date |
07/09/23 |
05/10/23 |
Qualification Results Publication Date |
07/09/23 |
05/10/23 |
Final Auction Information Pack Date |
07/09/23 |
05/10/23 |
Capacity Auction Submission Commencement |
21/09/23 |
19/10/23 |
Capacity Auction Submission End |
28/09/23 |
26/10/23 |
Capacity Auction Run Start |
28/09/23 |
26/10/23 |
Capacity Auction Completion Date |
03/10/23 |
01/11/23 |
Capacity Auction Provisional Results Date |
03/10/23 |
01/11/23 |
Capacity Auction Provisional Results Publication Date |
10/10/23 |
08/11/23 |
Capacity Auction Approval Date |
02/11/23 |
05/12/23 |
Capacity Auction Results Date |
09/11/23 |
05/12/23 |
Performance Security Date |
21/12/23 |
16/01/24 |
We apologise for any inconvenience this may have caused.
If you have any questions on the above, please contact do not hesitate to contact us.