REMIT Update
Affected Period
17/05/2019
Status
Open
Category
European Transparency
Run Type
N/A
Created
Last Updated
Update to the REMIT report published on the EirGrid Website under
customer-and-industry/general-customer-information/outage-information
Turlough Hill Unit 4 TH4 (GU_400363) have updated their plan prior to their beginning their scheduled outage. The unit will be generating from 07:00 on the 18th of May in order to empty the reservoir. The unit expects to finish generating at 11:31 on the 18th of May. The unit will then be unavailable until 17:00 on the 14th of June.
Tarbert Unit 1 (GU_400750) have updated the end of their current outage and expect to be available from 17:00 on the 17th of May.
If you have any queries please contact OutagePlanning@eirgrid.com
Disclaimer: This information is being provided to help market participants comply with the EU Regulation on Wholesale Energy Markets Integrity and Transparency (REMIT) (# 1227/2011) which specifies that market participants are obliged to fulfill the obligations described in Article 4 (1) and specifically that “Market participants shall publicly disclose in an effective and timely manner inside information which they possess...”.
Whilst it strives to ensure as high a level of accuracy as possible, EirGrid Group makes no warranties or representations of any kind with respect to: (a) the content of this email (including without limitation its quality, accuracy, and completeness), or (b) the content of any other website referred to or accessed by means of a hypertext link through this email.