Revised Weekly Constraints Update
Affected Period
Status
Closed
Category
Balancing
Run Type
Created
Last Updated
EirGrid and SONI have published a revised weekly constraints update for Week 21.
The revision includes an update to the 400kV Network transmission constraint group limit (S_NBMIN_MP_NB): There must be at least one unit on load when Ireland wind is less than 1,000 MW. This is required to support voltage in the West and the 400 kV network.
In addition, the value for ‘Maximum Moyle Export’ has been increased from 380 MW to 400 MW.
The weekly constraints update is published every Friday evening on the TSO Responsibilities page of SEM-O.com.