Revised Weekly Constraints Update
Affected Period
Status
Closed
Category
Balancing
Run Type
N/A
Created
Last Updated
EirGrid and SONI have published a revised weekly constraints update for the current Week 25.
The revision note :
- PBA and PBB must run from 23/06/2021 to 25/06/2021.
- New constraint group active from 18:00 22/06/2021:
Name: ''CT_HRS''
TCG Type: MW
Limit Type: X:=
Limit: 0 MW
Units included: AT2, AT4
The weekly constraints update is published every Friday evening on the TSO Responsibilities page of SEM-O.com, alongside the current monthly update.