Sample re-settlement Settlement Document
Affected Period
Status
Closed
Category
Balancing
Run Type
N/A
Created
Last Updated
Clarification 04/07/2019;
"In this instance you will see that all days excluding the 9th will be Initials as the 9th will be AH (Ad-hoc) , as this is the latest data."
All days excluding the 9th will be recalculated for M+4 from latest settlement run (initial) for X settlement date , the 9th M+4 will be re-calculated from Ad-hoc
There will be 7 days of M4 tracking, 6 days initial tracking and 1 day Ad-hoc tracking within the Settlement Documents
Dear Market Participant,
Please see attached sample Settlement Document xml from Week 2 ISEM test run 07/10/2018 – 13/10/2018.
This details the tracking data from Initial settlements, plus the latest settlement run for X settlement date from which re-settlement values will be calculated.
· The summary within the xml file data does not detail Initial & M+4 values individually, it will only detail the final monetary re-settlement values for the totals, interest, reallocations, sales & purchase totals for all charges codes.
· The report detail will show the sales and purchases previous & current per charge code
· Tracking Information will detail each charge code and is split between Initial, M+4 & AH.
Please also note that KIR defect 6042 does not affect participant SD reports. This defect was confirmed to only affect internal application UI screen. As such issue has been closed – No impact to market participants.