Settlement Documents are now available for the following dates:
Settlement Document 1:
M+4 BALIMB 26.05.2019 - 01.06.2019 - Wk 21 2019
M+4 BALIMB 02.06.2019 - 08.06.2019 - Wk 22 2019
M+13 BALIMB 09.12.2018 - 15.12.2018 - Wk 49 2018
M+4 CRM May 2019
Please note that the payment in and out dates on this settlement document have already been amended to reflect the late publication today.
Settlement Document 2:
INITIAL BALIMB 19.01.2020 - 25.01.2020 - Week 03 2020
Please note the dates within this settlement document have not been amended to reflect late publication today. Therefore payment in and out dates should be extended by +1 day.
MO Invoice for:
M+4 MO May 2019
Update 13:00:
SEMO would like to advise participants that Settlement Documents are now available for download. As a result of the delay, payment due dates will be adjusted accordingly.
Original:
SEMO would like to advise participants that there will be a delay with the publishing of Settlement Documents due by 12:00pm today. As a result payment due dates will be adjusted accordingly.
Our expectation is that Settlement Documents will be published at a later stage today.
A further update will be provided within the hour.
Kind Regards,