*Update* Settlement document 16.06.2023- issue with Ad hoc resettlement for CRM for April 2021
Affected Period
Status
Closed
Category
Settlement
Run Type
Created
Last Updated
Updated message 19/06/2023:
Dear Market Participant,
Following Friday’s Market Message, the team have further investigated the issue and it’s impacts.
We can confirm there will be no change to the payment in and out dates this week.
If you are having issues loading the Settlement Documents issued on Friday, these can be downloaded from MPI or please contact info@sem-o.com and one of the team will assist you to get a file that can be loaded into your system.
We apologise for any inconvenience caused.
Kind regards,
SEMO Settlements
Original message 16/06/2023:
Dear Market Participant,
We are aware of an issue with Ad hoc resettlement for CRM for April 2021 contained within today's Settlement Document. The billing period listed as weekly instead of monthly.
The invoice amounts for all PT’S are zero, however this may have caused some validation issues in your systems.
We will not be issuing a revised Settlement document today. We are currently reviewing the issue and will send an updated market message next week.
Apologies for any inconvenience this may have caused.
Kind regards,
SEMO Settlements