Revised Weekly Constraints Update
Affected Period
Status
Closed
Category
Balancing
Run Type
Created
Last Updated
Updated Message 25/01/2025 12:04 GMT
Dear Market Participant,
Please be advised that the below constraint has now been lifted.
Kind regards,
SEMO Team
Original Message 23/01/2024 16:14 GMT
Dear Market Participant,
EirGrid and SONI have published a revised weekly constraints update for the current Week 04 2025.
The revision note:
The below temporary Transmission Constraint Group note has been added:
Constraint:
The following units are ‘must run’ from 21:00 23/01/25:
- TYC
- GI4
- One of the following: MP1, MP3
- One of the following: AD2, WG1
- Four from the following: DB1, HNC, HN2, PBA, PBB
- MP5
- CGT8 (Sync Comp Mode)
Reason:
Security of supply during Storm Éowyn
The weekly constraints update is published every Friday evening on the General Publications page of SEM-O.com.
Kind regards,
SEMO Team